Executive summary
Choosing a predetermined time system (PMTS) is not a question of brand or fashion, but of technical-operational fit: required level of detail, process cycle time range, industrial sector, training budget and the need for interoperability with MES or ERP. This guide compares the four major systems in use —MTM, MOST, MTS and DMT— and their certified variants, with comparable criteria so that the decision is based on data rather than inertia.
1. Why PMTS remain the foundation of methods engineering in 2026
Predetermined Motion Time Systems (PMTS) encode the standard time of each basic human movement from high-speed films made under laboratory conditions. Unlike the stopwatch on the shop floor, they do not depend on the operator, the shift, or performance rating: the "should be" time is obtained before production, which makes it possible to:
- Establish standards that can be defended before a works council or an OEM customer.
- Simulate method alternatives before building the prototype.
- Feed digital twins and MES/ERP systems with consistent data.
The introductory article by Cronometras "Introduction to Predetermined Time Systems (MTM and MOST)" covers the fundamentals. Here we go into the comparative detail.
2. The common unit: TMU
All PMTS share a base time unit: the TMU (Time-Measurement Unit), where:
1 TMU = 0,036 seconds = 1/100.000 hour
Therefore, 1 second ≈ 27,8 TMU, and a standard minute ≈ 1.667 TMU. This standardization is historical: the MTM family was the first to define it, and MOST, MTS and DMT adopted it to make times comparable across systems. The numerical values are, however, different between systems, because each one models movement with a different level of granularity.
Caution: 53,4 TMU is not the same as 53,4 TMU in another system. The unit is the same, but the physical meaning of the value changes. Comparing bare figures between different PMTS is one of the most common mistakes in industry.
3. MTM (Methods-Time Measurement)
3.1. History and variants
MTM was developed by H. B. Maynard, J. L. Stegemerten and J. G. Schwab at Westinghouse and published in 1948 in the book Methods-Time Measurement. Afterwards, the MTM Association (headquartered in Hamburg, Germany, with offices in more than 30 countries) has standardized and maintains it. From the base system, several certified official variants have been published:
| Variant | Basic motions | Typical application |
|---|---|---|
| MTM-1 | Detailed basic motions (Reach R, Move M, Turn T, Grasp G, Position P, Release RL, Disengage D, Apply Pressure AP, Crank C, Eye Travel ET and body motions) | Detailed analysis, workstations with cycle time > 1,6 min, precision discrete manufacturing |
| MTM-2 | 9 (summary) | Medium and repetitive cycles, series production |
| MTM-UAS (Universal Analysis System) | 9 + simplified rules | Mixed work cells, rapid training of analysts |
| MTM-MEK | Subset oriented to automotive assembly | Automotive sector and Tier-1/Tier-2 suppliers |
| MTM-H | Pre-grouped sequences for hospitals | Healthcare logistics, operating rooms, hospital pharmacy |
3.2. Range and system data
According to the official MTM-1 Data Card (MTM Association, 2019 edition), the highest value in the system corresponds to P2 (Position with difficult fit) = 53,4 TMU and the minimum values to G1A (closed Grasp) = 2,0 TMU. In total, the MTM-1 data card contains approximately 900 TMU values.
3.3. Strengths and weaknesses
- Strengths: maximum precision, healthcare coverage (MTM-H) and automotive coverage (MTM-MEK), international recognition, regulated four-level training (Basic, MTM-1, MTM-2, MTM-UAS).
- Weaknesses: slow analysis (between 5 and 20 minutes per operation), high training cost (≈ 2.500–4.000 € per analyst in an official course, indicative figure), closed data card that requires updating by the MTM Association.
4. MOST (Maynard Operation Sequence Technique)
4.1. History and variants
MOST was developed by K. B. Zandin in the Swedish division of H.B. Maynard & Co. (1967-1972) and introduced in the USA in 1974, as a fourth-generation system. It does not list basic motions: it encodes the operation with standard sequences. Subsequently, additional variants were published (according to Wikipedia, MOST):
| Variant | Level of detail | Application |
|---|---|---|
| BasicMOST | Tens of TMU (10–1.000 TMU/op.) | General assembly, logistics, medium-cycle operations |
| MiniMOST | Individual TMU | Micro-operation analysis, method adjustments |
| MaxiMOST | Hundreds of TMU | Macro-activity processes (e.g. vehicle movements, complete lines) |
4.2. Structure of the sequences
Unlike MTM, MOST does not list 19 basic motions, but works with three standard sequences:
- General movement sequence (ABG ABP AB): movement of the body and of objects.
- Controlled movement sequence (ABG Apx Bpx): guided movements into a position.
- Tool use sequence (ABG AB MxI T AB): operations with a tool on the workpiece.
Each sequence is coded with letters and numeric indices that describe the complete operation. This reduces analysis time: whereas an MTM-1 may take 15 minutes per operation, a BasicMOST is resolved in 2–5 minutes for similar operations.
4.3. Strengths and weaknesses
- Strengths: analysis 3–5 times faster than MTM-1 (indicative figure), broad coverage (includes complete body motions), moderate learning curve.
- Weaknesses: lower precision in short-cycle micro-operations (where MTM-UAS wins), less widespread in Europe than in the USA and Australia, dependence on H.B. Maynard for official training.
5. MTS — Canadian system
5.1. Characteristics
The MTS system is a Canadian predetermined time system oriented to short cycles, maintained by the organization MTS Canada. Its distinguishing features:
- Only 8 basic motions (Reach, Move, Turn, Grasp, Position, Release, Press, Crank).
- Tables with TMU values calculated from a broad database of short cycles.
- Designed for the Canadian lumber and pulp and paper industry, it is now also applied in food, chemicals and general manufacturing.
5.2. Strengths and weaknesses
- Strengths: simplicity (8 vs 19 motions), fast learning, lower training cost than MTM-1.
- Weaknesses: limited international presence (strong in Canada and northern Europe, weak in Spain and Latin America), data card with less coverage of atypical cases.
6. DMT (Dimensional Motion Times)
6.1. Characteristics
DMT (Dimensional Motion Times) is the newest and least widespread system in the group. It is an evolution of MOST that integrates the principles of MTM into a simpler modular structure.
- Structure: combines MOST standard sequences with reduced MTM tables.
- Application: mainly industries that already use MOST and need to go down to individual TMU level without jumping to MTM-1.
- Coverage: North America and the United Kingdom; marginal presence in Spain.
6.2. Strengths and weaknesses
- Strengths: bridge between MOST and MTM-1, avoids double training.
- Weaknesses: small critical mass of certified analysts and very limited support.
7. Overall comparison table
| System | Basic motions | Average analysis time (indicative) | Relative training cost | Sectors where it dominates | Certified variants |
|---|---|---|---|---|---|
| MTM-1 | detailed | 10–20 min/op | High | Automotive, hospitals, electronics, defense | MTM-1, MTM-2, MTM-UAS, MTM-MEK, MTM-H |
| MOST | 3 sequences | 2–5 min/op | Medium | Aerospace, general assembly, logistics | BasicMOST, MiniMOST, MaxiMOST |
| MTS | 8 | 3–7 min/op | Medium-low | Pulp/paper, food, chemicals, general manufacturing | MTS base, MTS Pro |
| DMT | MOST + light MTM | 4–8 min/op | Medium | Mixed industries, MOST→MTM transition | Standard DMT |
8. How to choose the right PMTS: 6 operational criteria
8.1. Cycle time range
- Cycles < 5 seconds → MTM-1 or MiniMOST (fine granularity is essential).
- Cycles between 5 s and 2 min → MTM-UAS, BasicMOST or MTS.
- Cycles > 2 min → BasicMOST, MaxiMOST or DMT.
8.2. Method variability
- Lines with high product rotation and frequent variants → BasicMOST or MTS (speed of re-analysis).
- Stable lines with a single product for years → MTM-1 (maximum amortizable precision).
8.3. Sector
- OEM/Tier-1 automotive: MTM-1 or MTM-MEK.
- Aerospace: BasicMOST / MaxiMOST.
- Hospital / healthcare sector: MTM-H.
- Chemicals / food / pulp and paper: MTS or BasicMOST.
- Logistics and picking: BasicMOST or MTM-UAS (see also Time Engineering in Logistics and Picking).
8.4. Budget and critical mass
- Available for premium training (> 4.000 € per analyst, indicative figure): MTM-1 + official variants.
- Medium available (1.500–3.000 €, indicative figure): BasicMOST or MTS.
- Mixed (several analysts with limited budget): MTM-UAS for its cost/coverage balance.
8.5. Interoperability with MES / ERP
- If the standards must be exported to a MES with a closed catalog, MOST generates fewer motions per operation (easier to map).
- If the ERP/MES ingests raw TMU, MTM-1 is direct.
- If the system is mixed, DMT can serve as an operational translator.
8.6. International homogeneity of the company
- Multinational with presence in Germany/USA/Mexico → MTM (the MTM Association has local representation).
- Operation concentrated in North America → MOST/DMT.
- Operation in Canada or northern Europe → MTS.
9. Migration between systems
In industrial practice it is common to start with MOST for speed and migrate to MTM-1 when the method stabilizes and forensic precision is needed. Three rules for migrating without losing data:
- Double analysis for 90 days on 5–10 witness operations; compare the deviation between systems before retiring the old one.
- Do not mix TMU between systems in the same catalog: if one operation is analyzed with MTM-1 and the next with MOST, the catalog loses coherence.
- Maintain analyst traceability (stamp or digital signature) in each record for standard audits.
10. How it integrates with Cronometras (app)
The app Cronometras works with times timed on the shop floor and transforms them into standard times by applying synthetic performance rating and ILO and TAL allowances. PMTS are complementary, not substitutive:
- Cronometras = empirical measurement (what happens).
- MTM/MOST/MTS/DMT = predictive modeling (what should happen).
- Both are cross-referenced in the master catalog of standard times for continuous audit.
For a mature industrial organization, the logical flow is:
- Analyze the method with a PMTS (MOST or MTM-1) → target standard.
- Time the reality on the shop floor with Cronometras, during the necessary cycles → observed time.
- Compare, detect drift and apply allowances.
This connects with the Standard Time Audit and with the New Paradigm of Industrial Time Study 2025.
11. Conclusions
- There is no universally superior PMTS: each one solves a specific problem.
- MTM-1 remains the benchmark for maximum precision and sector coverage, but requires investment in training.
- BasicMOST is the pragmatic choice to start with: it covers most discrete manufacturing cases at a fraction of the analysis time.
- MTS is a solid option for the process industry (chemicals, food, pulp/paper) with presence in Canada and northern Europe.
- DMT works as an operational bridge between MOST and MTM, without sufficient critical mass outside North America.
- Fit matters more than the name: a poorly implemented MTM-1 is worse than a well-maintained BasicMOST run by trained analysts.
12. References and sources
- MTM Association (2019). MTM-1 Data Card, official edition. Available at
mtm.org/fileadmin/user_upload/MTM-1_datacard_2019_EN.pdfandMTM-1_datacard_2019_ES.pdf. - Wikipedia: Maynard Operation Sequence Technique. https://en.wikipedia.org/wiki/Maynard_operation_sequence_technique
- Wikipedia: Methods-Time Measurement. https://en.wikipedia.org/wiki/Methods-time_measurement
- IMEKO TC10 (2020). Comprehensive Comparison of MTM and BasicMOST, as the Most Popular PMTS. https://www.imeko.org/publications/tc10-2020/IMEKO-TC10-2020-058.pdf
- TPT Productivity Team (July 2024). Predetermined Time Studies (MOST, MTM, MODAPTS). https://productivityteam.com/2024/07/predetermined-time-studies/
- UK MTM Association. MTM-1 Systems Description. https://ukmtm.co.uk/systems/mtm-1/
- Cronometras (January 2026). Introduction to Predetermined Time Systems (MTM and MOST). https://cronometras.com/es/blog/introduccion-a-los-sistemas-de-tiempos-predeterminados-mtm-y-most/
Do you want to apply a PMTS to your production line and contrast it with times timed on the shop floor? Request a Cronometras demo(https://cronometras.com/es/#contacto) and we will help you define the defensible standard your operation needs.
Don't want to do it yourself? We do it for you from €800