In a corrugated board plant there are two promises that are made outside the shop floor and paid for inside: the price of the box and the delivery date. Both are calculated, almost always, from the memory of how long the last similar order took. And both are broken for the same reason: no one has measured how long each operation really takes, what each format changeover costs, and how much of that time slips below the radar when the machine starts up, adjusts and starts up again.
If you run production, sales or the plant itself, this article is of interest for one specific reason: in a sector where the price of material is public and the customer compares three quotes in an afternoon, the margin is decided in machine time and in delivery reliability. What follows is a tour of how control of those two variables is lost in corrugated board and how it is recovered by measuring what really matters.
1. The problem is not the cardboard: it is the price calculated from memories
The typical conversation goes like this: a customer asks for forty thousand boxes of one format, sales looks at the history, the history says “last time it was thirty-odd minutes per thousand”, a slack percentage that someone set years ago is applied, and a price comes out. The order comes in. The plant produces it. And when the month is closed, the margin on that order looks nothing like what the quote promised.
No one has done anything strange. The problem is one of method: the time used to quote was not a standard time, it was a memory. And memories, in a plant with several shifts, three different box formats and flexographic printing that sometimes registers on the first try and sometimes does not, vary far more than it seems.
Producing without standard times does not mean producing without data. It means producing with data that are not comparable: the morning shift's production report, the afternoon operator's gut feeling and the planning spreadsheet that no one has reviewed since the last format changed. When the customer asks for explanations about a delay, or when the month-end close shows a margin nobody understands, the root cause is usually there.
2. A sector of tight margins, short lead times and heavy competition
To understand why this matters more in corrugated board than in other sectors, it helps to look at the industry figures in Spain. According to the data published by AFCO (Spanish Association of Corrugated Board Manufacturers) in its 2025 industry figures report, the Spanish corrugated board industry:
- produced 5.941 million square meters of corrugated board in 2025,
- consumed 3.347 thousand tonnes of paper at the corrugator,
- billed 7.168 million euros across direct and indirect activity,
- supports 26.875 jobs (12.775 direct and more than 14.100 indirect),
- and does so with 66 corrugating companies and 89 plants spread across the country.
Spain is Europe's third-largest producer of corrugated board. And demand comes, above all, from the food industry, which accounts for around 61% of consumption, followed by consumer goods, logistics and e-commerce, and capital goods.
Two things follow from this picture. First: you compete with dozens of plants that buy the same paper at similar prices, so the selling price is decided by your efficiency, not by your raw material. Second: your main customer (the food industry and logistics) works with short, seasonal lead times; a two-day delay in a food campaign is not an inconvenience, it is a serious problem for whoever buys from you. In this sector, quoting badly and delivering late are the same mistake seen from two angles.
3. Where the time goes in a corrugated board plant
Before talking about how to measure, it is worth understanding where time lives in this kind of plant, because it does not live where intuition says. The usual process has several linked stages:
- Sheet production at the corrugator. Paper is converted into corrugated board sheet. It is a continuous, high-volume process, where the time thieves are roll-change stops, splices and start-ups.
- Printing. Normally flexography, with one or several colors. Here the time that is eaten up is not the time printing is running: it is the setup (mounting printing plates, registration, color trial).
- Converting and die-cutting. Where the sheet becomes the box blank. By far the most widespread style is the American-style box — code 0201 in the catalogue of the European Federation of Corrugated Board Manufacturers (FEFCO) —, a flap box made with minimum sheet waste.
- Folding and gluing. A fast operation per unit, but sensitive to the glue-machine setting and to the format.
- Palletizing, bundling and dispatch. Where time is lost in manoeuvres, dock waiting and handling that no one has timed.
On top of all these stages sits the phenomenon that consumes the most margin and is measured the least: the format changeover. Changing from one format to another at the corrugator, in printing or in converting is not productive work, but it ties up machines and people. When each changeover “costs” half an hour in real terms and the plant does three a day, you are burning an hour and a half of daily capacity that appears in no quote. And when those changeovers have no standard time of their own, each shift solves them its own way: one in twenty-two minutes, another in forty-five.
There is an important nuance for whoever plans: the work on the shop floor is not homogeneous. The corrugator is a continuous process controlled by speed and stoppages; converting and gluing are manual, repetitive work, where the effort criteria that the International Labour Organization (OIT) sets out in its allowances do apply, together with those of the TAL, for load, pace or environmental conditions. And maintenance or warehouse tasks, far more irregular, are better approached through statistical observation than with a stopwatch — work sampling, the technique on which WorkSamp is based, provides answers there that an occasional time study cannot give —. Choosing well what is measured with which technique is half the job.
4. A standard time is not “how long it took last time”
At this point, it is worth clearing up the confusion that costs the most money: observed time is not standard time. The first is how long a specific operation took, on a specific shift, with a specific operator. The second is how long the operation should take when working at a normal pace, with a defined method and with the corresponding margins and allowances.
That difference translates into three very concrete business consequences:
- Price. If you quote with observed times that have not been normalized, every quote carries inside it the luck of the day it was measured. A well-built standard makes two salespeople arrive at the same price for the same order.
- Lead time. The delivery date sales promises is only defensible if planning knows how much the order will occupy on each resource. Without standards, planning fills gaps “by eye” and the lead time becomes a hope.
- Capacity. Do you need one more shift, a second gluer, or simply to organize the format changeovers better? Without standard times, that decision is made on feelings, and feelings usually cost a machine or a whole night of overtime.
How is a standard built that will stand up to the reality of the shop floor? By measuring repetitive work with a stopwatch and a defined method: observing the operation cycle by cycle, separating what is work from what is waiting or an incident, rating the pace on technical criteria instead of on the impression of the moment, and then adding the allowances and margins appropriate to the type of effort and to the working conditions of the station. That, which in the discipline of methods and measurement has a name and initials, is summed up for whoever runs the plant in one sentence: a number that everyone uses the same way, that can be defended in front of a customer, and that is updated when the process changes.
5. Simulated practical case: when the price did not cover the setup
To see all of the above together, an example with a medium-sized plant.
Simulated practical case
Example built for teaching purposes from plausible industry parameters. It does not correspond to a real implementation of CronometrasApp.
A plant with one corrugator, two converting lines and two shifts manufactures, among other formats, a high-turnover American-style box for a food-industry customer. The recurring order is 40.000 units. The quote was based on a history that assigned 26 minutes per thousand to the printing and setup phase.
When the operations are studied with a stopwatch, two findings emerge:
Finding 1: the price fell short exactly where the most work is done. The standard time for printing and setup, measured cycle by cycle and with the allowances applied to the manual work of mounting printing plates, turned out to be 34 minutes per thousand. That is: the quote allowed 26 minutes per thousand and the operation consumed 34. Over the full batch of 40.000 boxes (40 thousand-unit lots), that is 320 minutes of real work that were not in the price — about 5,3 hours of line time —. In percentage terms, almost a quarter of the real time of that phase (23,5%) was not covered in the quote. The order was not “expensive to make”: it was cheap to sell.
Finding 2: the format changeovers were a silent hole. The plant did three format changeovers a day on the converting lines. With no standardized procedure, each changeover took about 38 minutes on average. By defining the method, sequencing the tasks and timing the new procedure, the changeover was set at 22 minutes. The saving is 16 minutes per changeover: 48 minutes a day, 960 minutes a month, 16 hours of line time a month that become available again. With an indicative hourly line cost of 90 € (a parameter of the case, not a market reference), that is some 1.440 € a month, on the order of 17.000 € a year, plus 16 hours of capacity to absorb peaks without overtime.
Consequence for the lead time. Knowing how much each product reference really occupies on each resource, planning was able to go from promising “around fifteen days” to committing to twelve with no added risk: not because the plant worked faster, but because the promise stopped being calculated with numbers that nobody could defend.
None of these results required investing in new machinery. It required measuring, deciding on a method, and always using the same number.
6. How to decide what to measure first
The classic mistake is wanting to measure the whole plant in the first month. In corrugated board, the order that works best is this:
- The format changeovers. There are few of them, they repeat every day and their impact on capacity is immediate. If you only did this, the study would already have paid for itself.
- The three to five highest-turnover product references. The ones you produce the most thousand units of per year: a small standard error there is multiplied across the whole volume.
- The operations with the greatest variability. The ones that make two shifts produce different results: printing setups, gluing, palletizing.
- The rest, by economic impact. Not in alphabetical order, nor by whatever is most comfortable to measure.
A good prioritization criterion is to ask, for each operation: how much money a year passes through here? how much does it vary from one shift to another? does it appear in our quotes? Three high answers point to where to start.
7. From standard to price and lead time: what changes the following Monday
When the plant has reliable standard times, three things change quickly, and none of them requires changing management software:
- The quote is calculated with a common number. Sales stops asking for “the time it took last time” and uses the current standard. If an order is special, the deviation is estimated, not improvised.
- Planning stops filling gaps by eye. The production sequence is ordered knowing the real load per resource, and the lead time promised is the one the work queue allows.
- The margin review has an explanation. When an order comes out below what was expected, you can say whether it was due to time, material or an incident, because the calculation chain is documented.
This is where a time-and-motion analysis tool such as CronometrasApp comes in naturally. What it provides, said in plant terms and not in technical-manual terms: a digital on-screen stopwatch to measure each operation in its different modes (continuous tracking, by frequency or linked to a machine); synthetic performance rating, which the technician applies to the observed operation to normalize it; OIT and TAL allowances configurable by activity and condition; and standard times with their tolerances and margins, with the calculation chain visible. Studies are exported in PDF, Excel or JSON so that everyone can take them where they are used — a pricing spreadsheet, a planner, a conversation with the customer —. And for repetitive work, the element library and voice entry avoid having to time from scratch what has already been measured.
Integration with the customer's tool is, as in most solutions of this kind, a manual export of those reports: the advantage is not in promising magic connectors, but in that the number that is exported is a defensible number.
8. Six signs that you are producing without standard times (even if you have spreadsheets)
- Two salespeople quote the same order at different prices and both “are right”.
- The time for a format changeover depends on who is on shift.
- When an order is delayed, no one can say whether it was due to workload, an incident or a setup that ran long.
- Planning plans “with a safety margin” that nobody has calculated.
- At month-end close, the margin of the top orders does not match what was expected and the explanation is always the same (“prices”, “material”).
- The last time anything was measured on the shop floor was to justify a decision that had already been made.
If you recognize two or three of these signs, you do not have a discipline problem: you have a problem of numbers that do not exist.
9. The decision you can make this week
You do not need a six-month transformation plan. The specific, small and reversible decision is this: choose your three highest-volume product references and your three most frequent format changeovers, and measure those six points. In two or three weeks you will have standards for what moves the most money through your plant, and you will finally know whether that recurring order everyone believes is profitable really is.
With those numbers on the table, the conversation with sales changes tone (the price is defended with data), the conversation with planning changes tone (the lead time is committed with data) and the conversation with the customer changes tone (you can explain why your box costs what it costs and why it arrives when it arrives).
If you want to see how all this is measured on a screen, without changing the way your shop floor works, request a demo of CronometrasApp(https://app.cronometras.com/) and bring your highest-turnover formats: on those you see sooner than in any manual whether your times are where they should be. And if the challenge is working-time control for the shifts that sustain production, Induly solves the working-day and clock-in part; if before the study it is worth observing the irregular work of the warehouse or maintenance, WorkSamp covers work sampling; and if you are looking for a specialist in time measurement or productivity auditing, the ASETEMYT directory brings together industry professionals. All of these tools work under the umbrella of ProdCont, where industrial productivity solutions converge to measure, plan and decide with data.
The price of the box is already set by the market. What you can still decide is how much it costs you to make it and when you can promise it. In a corrugated board plant, that is directly margin.
Don't want to do it yourself? We do it for you from €800